PILING

Flood defence work in the USA with Bauer Foundation Corp.

In the United States the US Army Corps of Engineers (USACE), a federal agency of the Department of Defence, is responsible for the maintenance of dams and canals as well as flood defence.

 Construction of a cut-off wall at the Herbert Hoover Dike: Bauer was able to win three of the five task orders awarded to date

Construction of a cut-off wall at the Herbert Hoover Dike: Bauer was able to win three of the five task orders awarded to date

Currently, USACE is implementing several measures in a number of US states, and Bauer Foundation Corp., the American subsidiary of Bauer Spezialtiefbau GmbH, based in Odessa, Florida, is involved in a total of five major projects with a total contract value of approximately US$200 million.

Four of the construction projects - Herbert Hoover Dike Task Order 1, Task Order 3, Task Order 5 and the East St. Louis Cut-off Wall Project - are being executed by Bauer Foundation as a direct contractor of USACE. Bauer is involved as a subcontractor in the Teller Dam Project in Colorado.

Covering a total area of 730 square miles, Lake Okeechobee is the largest freshwater lake in the US state of Florida. Even though it extends over a length of about 35 miles and a width of about 30 miles, the lake is very shallow with an average depth of only 10ft and lacks a larger natural outflow. To protect against storm surges and flooding due to unusually high water levels, the existing dyke already received its first upgrade in the 1920s.

In the 1960s, additional canals, floodgates, and dams were added. Since the early 2000s, the US Army Corps of Engineers has been responsible for coordinating the rehabilitation of the approximately 140-mile long dyke around Lake Okeechobee.

In 2007, Bauer Foundation Corp. was initially tasked with the execution of cutter-soil mixing walls (CSM) along the south-eastern part of the dyke. Based on previous successful cooperation, Bauer was awarded further partial contracts for the years between 2011 and 2021, among them works on various culverts.

The current work phase includes the execution of a cut-off wall over a total length of 28 miles along the southwestern section of the dyke. Divided into five sections, also referred to as task orders, Bauer Foundation managed to win three of the five contracts: Task Order 1, Task Order 3 and Task Order 5.

For the first two sections, a total of approximately 3,325,000sqft of cut-off wall will be created to a maximum depth of approximately 66ft. Pre-drilling is required to remove organic deposits and loosen the occasional dense layers of sand and underlying weak limestone.

Subsequently, the actual soil mixing will begin with an RTG RG 27 drilling rig, using the CSM method which combines the features of a trench cutter while mixing the soils in-situ. In addition, the jet grouting method is used to connect the newly constructed cut-off wall with the existing culverts.

"Bauer, as the main contractor, was also tasked with the installation and subsequent removal of the necessary work platforms and is responsible for the access roads to the site. Following the works on the cut-off wall, we are also responsible for the revegetation and asphalting of the finished dyke and the quality-control tests and installation of monitoring instruments," explained Andrew Ebendick, project manager with Bauer Foundation Corp and in charge of Task Order 1.

"The work on the first two projects has already begun. Successful completion of the work on Task Order 3 is expected in the spring of 2022 and Task Order 1 in the fall of 2022," said David Millar, project manager for Task Order 3.

At the beginning of May 2020, Bauer Foundation was awarded Task Order 5 with a total value of approximately US$42 million. This is the last construction phase comprising a total length of almost 4.1 miles and the construction of approximately 750,000sqft of cut-off wall. In total, with the three construction phases, Bauer Foundation was commissioned with the execution of 17.7 miles out of the total of 28.6 miles of the south-western part of the Herbert Hoover Dike.

/

In order to restore the existing dyke on the east bank of the Mississippi, Bauer Foundation uses a grab and a cutter in combination to create a single-phase cut-off wall

In East St. Louis, Illinois, another existing levee system on the east bank of the Mississippi is receiving an upgrade. The existing levee structure is built on sandy ground that extends to the limestone bedrock at a depth of approximately 135ft. These sandy soils allow the water to undermine the levee contributing to erosion of the system, and neighbouring developments are under threat from frequent and severe flooding. To create a cut-off wall which will restore the existing dyke, Bauer Foundation uses a grab and a cutter in combination to create a single-phase cut-off wall with a self-hardening slurry.

"For this work, we use a DHG diaphragm walling grab and a BC 40 cutter, each attached to an MC 96 duty-cycle crane," explained Matteo Bertoni, project manager at Bauer Foundation Corp.

A total of approximately 570,000sqft of cut-off wall will be created over a length of 4,600ft and to a maximum depth of approximately 143ft.

Bauer, as the main contractor, was also commissioned with the provision of the necessary work platform, the installation and dismantling of the guide wall for the cut-off wall works, and with the final quality and lab testing. The location of the project poses a particular challenge: several important utilities cross the work front on the existing dyke on the banks of the Mississippi River. As a result, Bauer can only carry out the works within certain timeframes and at specific locations, all of which requires close cooperation with all participants. Mobilisation of the construction site went underway in March and completion of the overall project is scheduled for January 2022.

Specialist foundation engineering for the Teller Dam

The Teller Dam at the Turkey Creek River is located within the US Army post Fort Carson near Colorado Springs, Colorado. The remediation works at this location are also coordinated by the US Army Corps of Engineers.

/

Bauer is constructing a 350ft long cut-off wall to seal the Teller Dam

The main contractor, Komada LLC, commissioned Bauer Foundation Corp. with the execution of specialist foundation engineering works for sealing off the dam against potential infiltration and the associated erosion of dam material. For this reason, the cut-off wall works are carried out in two sections: at the left abutment and at the end of the dam, approximately 12,500sqft of secant pile wall will be created, apart from that, approximately 19,000sqft of grout curtain are produced via injection method to seal off potential infiltration paths.

The cut-off wall will be installed in the subsoil over a length of approximately 350ft and to a maximum depth of 120ft.

"The secant pile wall will be created with a diameter of 1,500mm, a Bauer BG 39 is going to be used," according to Cyril Bou Sleiman, Bauer Foundation Corp. project manager in charge. "The injection works for the grout curtain will commence this summer and a Klemm KR 806 will be used for this purpose." The works are expected to be completed by November.