Piling work begins for electrification of UK Midland Main Line railway

Electrification of main UK railway line begins as piling work gets underway

 Network Rail has begun piling work to replace overhead line equipment previously in place on the Midland Main Line route

Network Rail has begun piling work to replace overhead line equipment previously in place on the Midland Main Line route

As part of the Midland Main Line electrification, Network Rail will start to drive steel columns as deep as 7m into the ground to lay the foundations for the overhead line equipment needed to power electric and bi-mode trains in the future.

The multi-million-pound programme supports the UK government's ambitions for decarbonisation and aims to deliver a greener, more reliable railway to connect passengers right the way between London and Sheffield, via Nottingham and Derby.

This next phase of major work will see a 12-mile section between Market Harborough and Wigston brought up to speed to eventually connect the entire route, following recent upgrades between Corby and Bedford.

Most of the work will be done overnight while there are no trains running to keep railway workers safe and to keep disruption to a minimum.

This latest programme of piling will run until August 2023 to ready the line for electric wires to be installed throughout 2023.

Gavin Crook, principal programme sponsor for Network Rail, said: "Starting this next phase of work is a huge step forward for the Midland Main Line Upgrade. It adds to the important work we've already completed to transform journeys between London and Corby, and sees us work towards a fully electrified route.

"We're excited to offer passengers a more reliable, greener railway which is fit for the future, encourages more people to travel by train, and supports economic growth along the way."