INFRASTRUCTURE

Tunnel progress as HS2 completes first mile under the Chilterns

First mile of HS2 tunnels completed under Chiltern Hills on UK infrastructure project

 The view from within the first mile of the HS2 Chiltern tunnels looking south towards London

The view from within the first mile of the HS2 Chiltern tunnels looking south towards London

Launched in May, the 170m long tunnel boring machine (TBM) covered the first mile cutting through a mix of chalk and flint beneath the Chiltern hills just outside London.

Named ‘Florence' by local school children, the TBM is one of two identical machines excavating the twin 10-mile long tunnels. A second machine, named ‘Cecilia' is a short way behind, with both TBM expected to break out in around three years' time.

Designed specifically for the geology of the Chilterns, each machine is a self-contained underground factory, digging the tunnel, lining it with concrete wall segments and grouting them into place as it moves forward.

Welcoming the progress, HS2 Ltd Project Client Rohan Perin said: "The 10-mile Chiltern tunnel will take HS2 underneath the hills and safeguard the woodlands and wildlife habits above ground as well as significantly reducing disruption to communities during construction and operation of the new railway.

"Once complete, HS2 will offer low carbon journey options linking London with the major cities of the north and releasing capacity for more freight and local trains on our existing mainlines. It's great to see how much progress has been made over the summer and I'd like to thank the crew of Florence and all the tunnelling team for their hard work."

The first two TBM are operated by HS2's main works contractor, Align - a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick.

A crew of 17 people keep the machines running, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.

Align project director Daniel Altier added: "I am delighted with the progress that Florence has made since its launch in May, with Cecilia not far behind. All the spoil from the TBM is converted into slurry before being pumped back to our South Portal site, just inside the M25, where it is processed and used for landscaping on site. This is, and will continue to be, a huge logistical challenge, as Florence and Cecilia continue their journey through the Chilterns.

"Florence reaching the one-mile point is a great achievement. However, we still have a long way to go."

Each of the separate northbound and southbound tunnels will require 56,000 precision-engineered, fibre-reinforced concrete wall segments - which are all being made at the south portal of the tunnel, next to the M25. During her first mile, Florence and her crew have installed more than 5,500 separate segments, each weighing around 8.5t.

Approximately 2.7 million cubic metres of material will be excavated during the construction of the tunnels and used for landscaping around the south portal site. Once construction is complete, this will help create around 90 hectares of wildlife-rich chalk grassland habitats. Chalk grassland used to be widespread across the hills of southeast England and are considered habitat of international conservation significance with just 700ha left across the Chilterns.

In total there will be ten TBMs on the HS2 project - working to create 64 miles of tunnel between London and the West Midlands including major tunnels on the approach to London and Birmingham.

Got a story? Email: duncan.moore@aspermontmedia.com