INFRASTRUCTURE

Tunnel progress as HS2's 'Florence' and 'Cecilia' reach Chesham Road

HS2's TBM on target to finish 10 miles of tunnelling for high-speed rail link this year

 HS2’s TBM Cecilia within the northbound Chiltern tunnel

HS2’s TBM Cecilia within the northbound Chiltern tunnel

The 2000t machines are now 90% of the way through their two-and-a-half-year drive between the M25 and South Heath in Buckinghamshire to create the twin-bore tunnel.

In total, HS2 will require 64 miles of tunnelling, with five tunnel boring machines (TBM) already in the ground, three more ready to go and another two due to be delivered this year. Once complete, HS2 will help improve connections between London, Birmingham and the North while creating space on the most congested part of the existing West Coast Main Line.

Each Chiltern TBM is a 170m long self-contained underground factory, digging the tunnel, lining it with 56,000 concrete segments to form rings and grouting them into place as it moves forward.

Designed for the geology

Designed specifically for the geology of the Chilterns, the machines were launched in Summer 2021 from a site near the M25 and have already excavated approximately 2.8 million cubic metres of chalk and flint.

As well as digging and lining the tunnels, engineers have also completed the excavation of four other shafts that will provide ventilation and emergency access near Chalfont St Peter, Chalfont St Giles, Amersham and Little Missenden with work now happening to create the internal structures and the headhouses on the surface.

The 42m deep shaft near Great Missenden - which the TBM has now reached - is largely hidden behind a hedge and line of mature oak trees next to the B485.

A ‘headhouse' will be built on top of the shaft designed to resemble local farm buildings with new planting to help blend it into the surrounding landscape. The Chesham Road shaft will only be used for emergency access, while the others will also contain ventilation equipment.

The two TBM are operated by, Align - a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick. Each machine has a crew of around 15 people, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.

Tunnelling achievement

Didier Jacques, Align's underground construction director, said: "With our first TBM Florence having reached our fifth shaft at Chesham Road and our second TBM Cecilia due to reach the shaft shortly, this a great achievement for not only the tunnelling team, but also the supporting teams on the surface at the South Portal, manufacturing the concrete segments required to line the tunnels and processing the spoil from the tunnels.

"We are looking forward to continuing the good progress with the TBMs, which are due to complete their drives early this year." 

Approximately three million cubic metres of material - mostly chalk and flint - will be excavated during the construction of the tunnels and used for landscaping. Once construction is complete, the temporary buildings at the south portal will be removed and the site landscaped with around 90 hectares of wildlife-rich chalk grassland habitats.

Alongside the Chiltern tunnels, two TBM are currently excavating the London tunnels with two more due to launch soon. One TBM is excavating the Bromford tunnel in Birmingham with another ready to go. Two TBMs which will excavate the Euston tunnels are due to be delivered to site next year.

Got a story? Email: duncan.moore@aspermont.com